Solved by verified expert:QUESTION 1
Failure to quantify project objectives raises the risk that the project won’t achieve the?
Statement of work
Project plan
Customer’s expectations
Project control
QUESTION 2
How do we know if the project is successful. One aspect is validating scope. Scope validation is the process of the project customer accepting?
Project deliverables
Project scope
Project WBS
Project inspection
QUESTION 3
The change control system should do several things for the project management team including document all change requests, track each change requests document approval levels required for change, and
Restate scope requirements
Indicate how change impacts communications
Provide the status of each change request
How change impacts quality
QUESTION 4
The approach maps ideas to show the relationship among requirements and the difference between requirements.
Mind Mapping
Context Diagram
Network Diagram
Funding limits
QUESTION 5
These diagram shown the relationship between elements of an environment.
Mind Mapping
Context Diagram
Network Diagram
Funding limits
QUESTION 6
There are seven key processes associated with project time management.
The seven processes are interdependent on one another and on the _________ of the project?
Schedule
Activities
Estimations
Life cycle
QUESTION 7
The planning technique that focuses on the immediate while considering the big picture and utilizes iterations of planning is called?
Waterfall method
Rolling wave
Agile project management
Scrum
QUESTION 8
Part of the process of sequencing events is the development of network diagrams. A network diagram shows the relationship of the work activities and how the activities progress start to finish. What is the most common method for arranging work visually into a network diagram?
Activity on node
Activity on arrow
Precedence diagramming method
Activity sequencing
QUESTION 9
These dependencies are the natural order of activities.
Mandatory dependencies
Discretionary dependencies
External dependencies
Internal dependencies
QUESTION 10
What is the most accurate project estimating methods for time and cost?
Published estimating data
Bottom-up estimating
Parametric estimating
Sequencing estimation
You will get a plagiarism-free paper and you can get an originality report upon request.
All the personal information is confidential and we have 100% safe payment methods. We also guarantee good grades
Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.
You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.
Read moreEach paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.
Read moreThanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.
Read moreYour email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.
Read moreBy sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.
Read more