QuestionAnswered step-by-stepRecently, Phil Harris, the Production Control Manager at Brunswick,…Recently, Phil Harris, the Production Control Manager at Brunswick, read an article on Time-Phased Requirements Planning. He was curious about how this technique might work in scheduling Brunswick’s engine assembly operations, and decided to make an example to illustrate the use to Time-Phased Requirements Planning.Phil’s first step was to make a master schedule for one of the engine types produced by Brunswick – the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the past twelve weeks, and is shown below. Engine Assembly Master ScheduleWeek 1 2 3 4 5 6 7 8 9 10 11 12Demand 18 5 12 10 17 22 10 9 5 20 Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the Gear Box and the Input Shaft, are shown in the Product Structure Diagram shown here. Phil noted that the Gear Box is assembled by the Sub-Assembly Department, and is subsequently sent to the main engine assembly line. Therefore, the engine assembly master schedule determines the weekly gross requirements for the Gear Box. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in the Product Structure Diagram to indicate the three manufacturing stages that are involved in producing an engine: the Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop.The manufacturing lead times required to produce the Gear Box and Input Shaft components are also indicated in the Product Structure Diagram. Note that two weeks are required to produce a batch of Gear Boxes, and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub-Assembly Department stockroom before Monday morning of the week.In preparing the MRP example Phil made the following assumptions: Twenty-two gear boxes are on hand at the beginning of Week 1, and eight gear boxes are currently on order to be delivered at the start of Week 2.Forty-five input shafts are on hand at the start of Week 1, and 25 are scheduled for delivery at the beginning of Week 2. Initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Gear Box Requirements Input Shaft Requirements Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gearbox and input shafts. These costs are as follows:Part Cost Gear Box Setup = $85/order Inventory Carrying Cost = $2/unit/week Input Shaft Setup = $40/order Inventory Carrying Cost = $2/unit/weekQuestionsQuestion 1. Complete the MRP table for Gear Box using the lot-for-lot (L4L) lot sizing technique. Use the numbers in the engine assembly master schedule, directly, for the weekly Gear Box gross requirements. What are the total costs of schedule for Gear Box based on the L4L technique? Gear Box Requirements (Lot size: L4L)Week: 1 2 3 4 5 6 7 8 9 10 11 12Gross Requirements Scheduled Receipts Projected Available Balance Net Requirements Planned Order Receipt Planned Order Release (2 marks)Gear Box Total Cost ($)Total setup cost Total inventory cost Having the completed MRP table for Gear Box, based on the L4L lot sizing technique, answer the following questions: Question 2. Complete the MRP table using the lot-for-lot (L4L) lot sizing technique for Input Shaft. What are the total costs of schedule for Input Shaft based on the L4L technique? Input Shaft Requirements (Lot size: L4L)Week: 1 2 3 4 5 6 7 8 9 10 11 12Gross Requirements Scheduled Receipts Projected Available Balance Net Requirements Planned Order Receipt Planned Order Release (2 marks)Input Shaft Total Cost ($)Total setup cost Total inventory cost Question 3. Complete the MRP table using the EOQ lot sizing technique for Input Shaft . Assume the total annual demand for Input Shaft is D= 2288 units. what are the total costs of schedule for Input Shaft based on the EOQ technique? }Question 3 .Input Shaft Requirements (Lot size: EOQ)Week: 1 2 3 4 5 6 7 8 9 10 11 12Gross Requirements Scheduled Receipts Projected Available Balance Net Requirements Planned Order Receipt Planned Order Release (2 marks)Input Shaft Total Cost ($)Total setup cost Total inventory cost Question 4.Complete the MRP table using the least total cost (LTC) lot sizing technique to determine the first planned order quantity for Input Shaft. The second order quantity must meet the requirements of Input Shaft to the end of week 12. What are the total costs of schedule for Input Shaft?Question 4.Input Shaft Requirements (Lot size: LTC)Week: 1 2 3 4 5 6 7 8 9 10 11 12Gross Requirements Scheduled Receipts Projected Available Balance Net Requirements Planned Order Receipt Planned Order Release (2 marks)Input Shaft Total Cost ($)Total setup cost Total inventory cost Question 5. Complete the MRP table , using the least unit cost (LUC) lot sizing technique to determine the first planned order quantity for Input Shaft. The second order quantity must meet the requirements of Input Shaft to the end of week 12. What are the total costs of schedule for Input Shaft? Question 5.Input Shaft Requirements (Lot size: LTC)Week: 1 2 3 4 5 6 7 8 9 10 11 12Gross Requirements Scheduled Receipts Projected Available Balance Net Requirements Planned Order Receipt Planned Order Release (2 marks)Input Shaft Total Cost ($)Total setup cost Total inventory cost Engineering & TechnologyIndustrial EngineeringOperations ManagementBUS 3501Share Question
You will get a plagiarism-free paper and you can get an originality report upon request.
All the personal information is confidential and we have 100% safe payment methods. We also guarantee good grades
Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.
You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.
Read moreEach paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.
Read moreThanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.
Read moreYour email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.
Read moreBy sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.
Read more