Expert answer:Problem-Based Learning (PBL) Scenario: Amazing Coffee Houses (ACHs)Company Biography Amazing Coffee Houses (ACHs) is a small but established company in the coffee industry. It is based in northern Chicago, IL and employs over 100 workers locally in its 10 stores. Its current Chief Executive Officer (CEO) and Chairman of the Board, Sam Ryder, founded the company back in 1994 with his wife, Gloria Ryder. Gloria has served as the company’s Chief Financial Officer (CFO) since it was founded. Both Sam and Gloria graduated from the #1 ranked MBA program in the country and bring a lot of corporate experience to the business. Sam was a Senior Vice President (SVP) in Marketing and Sales at another company for many years before deciding to venture off to start ACHs with his wife. Gloria also worked for that same company and held the position of Finance Director. The company is known for its own brand of gourmet coffee and low fat donuts, as well as for their own line of stainless steel coffee mugs that are able to keep drinks hot for 12 hours straight. The workforce is comprised mostly of bakers, managers, baristas, greeters, clerks, and cashiers. They also work closely with several large suppliers and distributors in the United States.ProblemThe company has a loyal customer base throughout Chicago and is known for its personalized service and quality food and drinks. Because the economic conditions have greatly improved throughout the United States and the company now has a well-established name and brands, ACHs is looking to expand in markets beyond Chicago. The first market it has made a decision to expand into is 81 miles away, Milwaukee, WI. The company has worked through a local real estate agent and was able to strike a great deal on a 10-year lease in a great location. Management thinks Milwaukee is where the next 10 stores will be opened. However, Sam and Gloria have never operated a multi-state business before and are worried they will fail to accomplish their expansion goal timely. Sam has made it clear to Gloria that one day, his vision is to take ACHs to every city in America.OpportunitySam has no project management experience and has decided to hire a project manager to manage the expansion project in Milwaukee, WI. After thorough evaluation and dozens of interviews, they have asked Jim Young, a rising star at the company, to take on the role of project manager to lead a team of five people from different departments to create a project plan for the new site. Jim Young currently serves as a store manager for the biggest two coffee shops. Prior to this role, he worked as a store supervisor for the company. During his time with the company, he has worked on many of the new shop development projects as a team leader and helped to renovate some of the company’s existing shops. People in his business units speak highly of his leadership and coaching style. Though Jim has worked on project teams and supervised functional departments, he has never acted as the project manager before. He knows there are a lot of moving parts in managing a project. He is worried about his ability to lead a new team of people with whom he has never worked before. He is concerned about his lack of experience and knowledge to manage the entire life cycle of a project from start to finish within budget, quality, time, and scope. In previous projects, he remembers Sam and Gloria having differences in budget, scope, and resource allocation, which caused a lot of confusion among the project team members and vendors. Jim is also concerned that their personal relationship will interfere in this project.You will be working with Jim Young as a project team member with four other professionals in the company. You have only worked at ACHs for 4 years. Prior to your tenure at ACHs, you worked as an associate project manager for a construction company on the West Coast. You have worked on many different projects and are familiar with project management terms, methodologies, tools, and techniques. You earned several certifications relating to project management including a PMP and have an MBA in logistics. Although, you have never worked with Jim Young or anyone else on the new team, you are very excited about the opportunity to make a difference. Project Background DetailsAmazing Coffee Houses (ACHs) is a coffee shop that will be located in Milwaukee, WI. We have been able to purchase our own building within the city near Milwaukee’s top tourist attraction site near the Gold Rock Museum. The building is not renovated. Our market analysis of Milwaukee, WI indicated the city is the top city for coffee drinking in WI. Because we’re close to the city’s museum, we plan to become the top destination for local and American and foreign customers who visit Milwaukee each year. Our customers will have a wide range of coffee flavors to choose from including dark roast to light roast as well as specialty flavors throughout the year. They will also enjoy freshly baked low-fat donuts that aren’t available anywhere in the state. ACHs will hold true to its vision and mission of providing customers with a premier café experience. By creating a new twist for the café experience, ACHs will increase sales by more than $125,000 over the next three years and maintain a gross margin of 70%. The shop is 5,500 square foot of open space. Our plan is to have 2 bathrooms, a coffee bar, and enough tables to seat at least 50 customers. This is a coffee shop that also makes and sells donuts. The renovation must account for all that is needed to get the shop ready for both coffee and donuts. The project has an initial budget of $650,000. It is now January and Sam and Gloria would like the new location to be up and running no later on July 4th. Note: The example companies, organizations, products, people, and events depicted herein are fictitious. No association with any real company, organization, product, person, or event is intended or should be inferred.Additional InformationJim asked you to join him to present the team’s leadership discussion to Sam and Gloria. The meeting got a little heated, but nothing went beyond your control. Overall, the meeting went very well. You addressed your concerns, highlighted some key problem areas that were shared by the rest of the team, and connected everything back to how their actions are impacting the success of the project. They now realize that their behaviors and actions are putting the project at risk along with many project risks you and the team have identified.They were also pretty embarrassed with the type of behaviors they displayed in the meeting as the company leaders. Both Sam and Gloria were very receptive to the ideas that you presented to them. In fact, so receptive that they both said they see a lot of leadership potential in you.”We are both sorry about the whole ordeal. We will both work together to control our emotions and not let it take over us again,” says Sam.”Yes I agree. I will approve the project budget, but to ensure everyone is on the same page and that project risks are managed properly, we need to see a simple project communication plan and a risk register. We need to understand your approach better going forward,” says Gloria.Jim turns to you, handing you a template for both the risk register and the communications plan. “You have done such an excellent job throughout this entire project. Would you be willing to complete these plans?””Of course.” you say. “Because of this incident and the leadership that you have displayed over the past few months, we would like you to take over Jim’s position as the new project manager,” says Sam to you.AssignmentBack at your desk, you start filling out the risk register template. For your risk register, you will need to define 5 negative risks and 5 positive risks and fill out the rest of the information in the template. For your communications management plan, you need to account for all communication types with your stakeholder. Please follow the instructions in the template for both deliverables.Please submit your assignment.For assistance with your assignment, please use your text, Web resources, and all course materials.Course Objectives:Formulate a project structure appropriate to program scope and overall organizational structure.Synthesize project management knowledge by evaluating a major project for project success in a comprehensive case study of that project.Model Answer:The template should be completed, including identification of 5 positive and negative risks.COMPLETE THE TEMPLATE AND ALSO IN A WORD DOCUMENT ADD AN INTRODUCTION, AN EXPLANATION OF YOUR POSITIVE AND NEGATIVE RISKS AND CONCLUSION. ADD 6 REFERENCES, USE APA FORMAT
risk_register_template__3_.xlsx
Unformatted Attachment Preview
Risk Register Workbook Instructions
This template is to be used for identifying risks and creating plans for how to avoid them (negative
risks) or how to make them happen (positive risks) and what to do if they happen (contingency plans)
and managing them throughout the project.
The first sheet, titled Risk Register, shows a number of fields to use for gathering the following
information about risks.
Risk ID is some unique value that identifies the risk.
Risk Name is a short description of the risk.
Risk Description “If this risk occurs, then what impact will it have on the project?” It should be
Impact as rated on a very low, low, medium, high, and very high scale.
Probability as rated on a very low, low, medium, high, and very high scale.
Risk Ranking: Using the risk matrix found on the right on the Risk Register sheet, detemine the color
Positive/Negative: Is this risk a positive risk (an opportunity) or a negative risk?
Proactive Response Plan is a detailed plan of what changes will be made to the project, project
scope,
and/or
proactively of
to how
try toyou
make
risk if
happen
(positive
risk) ororstop
it if ittoisoccur.
a
Trigger
EventWBS
is a description
willthe
know
the risk
has occurred
is about
Reactive Contingency Plan is the description of what you plan to do if the risk happens. How will
Form P-4
Project Manager: Name
(816) XXX-XXXX
Form P-4
Project Manager: Name
(816) XXX-XXXX
Risk Register
ID
Risk Name
Risk Description
Impact
VH,H,M,L,VL
Example: please remove
before completing
1 document. Critical
equipment does not
arrive on time.
If critical pieces of
equipment do not arrive
H
on time, the project will
fall behind schedule.
Probability
Risk Ranking
VH,H,M,L,VL
What is the risk color code ?
H
Red
2
3
4
Form P-4
Project Manager: Name
(816) XXX-XXXX
Positive/Negative
Proactive Response Plan
Is this a positive or negative risk What proactively can be attempted to make
from the risk matrix?
the risk happen or prevent it?
1. Add activities to the WBS to ensure with
the manufacturer that the equipment is
being built or shipped as required. 2. Have a
member of project team go to the
Negative
manufacturing plant to ensure equipment
parts are in progress and on schedule. 3.
Add steps to the WBS to ensure the
manufacturer ships on time. 4. Add steps to
WBS to track the shipment as needed.
ID
Risk Name
Form P-4
Risk Description
Impact
Probability
Risk Ranking
Project Manager: Name
(816) XXX-XXXX
Positive/Negative
Proactive Response Plan
Trigger Event
Reactive Contingency Plan
What do you think will What are your backup plans if the risk
trigger the event?
should occur?
Parts do not ship on
assigned date.
If possible, have a backup supplier
identified and standing by.
Impact
Very high
High
Medium
Low
Very low
Very low
Low
Medium
Probability
Risk Matrix
Form P-4
Project Manager: Name
(816) XXX-XXXX
High
Very high
Trigger Event
Reactive Contingency Plan
Form P-4
Project Manager: Name
(816) XXX-XXXX
…
Purchase answer to see full
attachment
You will get a plagiarism-free paper and you can get an originality report upon request.
All the personal information is confidential and we have 100% safe payment methods. We also guarantee good grades
Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.
You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.
Read moreEach paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.
Read moreThanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.
Read moreYour email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.
Read moreBy sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.
Read more